On Friday, March
13, due to the heavy volume of air traffic in the immediate area of
interest for the eclipse (est. 15 eclipse flights plus crossing
trans-Atlantic traffic),
Isavia (Icelandic Air Traffic
Control) issued a
directive
restricting eclipse flight operations only along two specific
"tracks" designated "Eclipse East" and "Eclipse West". The names
reflect Isavia's intention to develop two specific corridors flanking
(and roughly but not exactly parallel to) and equi-spaced by about 8 NM
on either side of centerline. Our flight (AB B737-800/DUS; later
designated AB 1234) was an assigned a flight level of 35,000 ft (FL
350) on the East track, the other two Air Berlin flights (AB
A320-200/DUS and AB A320-200/ZHR) were respectively assigned FL350 and
FL340 on "Eclipse West". At that point I was asked to develop
revised Totality Run scenarios for all three AB flights for delivery to
(and approval by) Isavia by way of AirEvents and Air Berlin.
The Isavia"tracks" were defined by way points of their creation
provided in the directive to be used with "no deviation". The way
points, however were quantified in units of 15 minutes of arc (!) in
Lat/Lon, so could not (and did not) exactly "parallel" centerline, and
in fact had inflections (course changes!) at the way point track
vertices. Moreover, to ascertain the location of centerline in
defining the "east"/"west" approximations for the two-tracks, Isavia
consulted the NASA (Fred Espenak's) eclipse web site -- apparently not
realizing the information provided there in was for sea level
only! As a result the "east" track was shifted by about 15.5 NM
from centerline (at 09:43:30 UTC), while the "West" track was actually
very close to centerline, for aircrafts operating at ~ 35,000 ft.
As a result, with replanning summarized below, the two AB A320 flights
on the "west" track ended up very close to at-altitude centerline.
Click
HERE for the FINAL (approved)
revision for the three AB flight totality runs, defined simply by three
waypoints conforming to the Isavia restrictions. For
"simplicity", and confined between Isavia waypoints, in iterated
replanning I had put all three AB totality runs with mid-eclipse
intercepts at 09:43:30 UTC, with the two A320's on the "west" track
altitude stacked by 1,000 ft (so AOK for the same time-correlated UTC
for mid-eclipse).
Note that the
predicted
duration(s) of totality I had given in the above linked summary
document were for
a no-wind condition only used
for planning purposes. With actual winds aloft, to maintain the
requisite time-correlated ground-track, the aircraft ground speed (and
thus duration of totality) would be different. The "no wind"
prediction (with lunar-limb profile corrections, of course) for "AB
1234" (the AB B737/DUS) flight was 03m 42.7s on the "east" track, and
03m 45.7s for the two A320 flights on the "west" track.
Re-planned Totality Run for AB/B737-800 DUS (AB 1234)
From a frame-by-frame examination of the original (15 Mby)
images, the duration of totality as measured from the complete
extinction of all photospheric Baily's Beads was 03m 39s ± 0.5
s. In (additional) detail (as provided to our pilots), an intermediate
time-correlated way points for C2 was hit nearly dead on (1/2 second
late), but C3 was hit appx 3-1/2 seconds "early". The difference?
WIND (as expected).
Here is the rest of the story... Just as we were completing our
totality run and staring our turn back to Dusseldorf, I went back onto
the flight deck to get a winds aloft reading from the aircraft FMS
(flight management system) display. You can see that as 46 knots
from 341 degrees true (top left of the right hand display). This
was just about 6 minutes after mid eclipse, and the winds MAY have had
some variability during the totality run, but this is a
first-order approximation much better than the a prior simplistic "no
wind" condition.
Note the duration of totality: 3m 39s --
as measured by complete photospheric extinction with frames from the
2 fps imaging camera. I do not know the wind vector for the two
AB
A320 aircraft, so I cannot compute the exact circumstances for those
aircraft. However, as they were "only" ~ 30 NM away, and at the
same/similar altitude, it is likely the winds were similar during the
totality run, and hence one may expect a very similar reduction of ~ 4
sec in their duration of totality.
Post-Facto, Back on Terra Firma
Click
HERE to see happy faces at 2x.
And... as known, we were not alone. Here (below) a visualization
of the "crowded" skies from flightradar24.com. Looks like,
somehow, one aircraft (FYG = Flying Group, Belgium) ended up between
the Isavia East and West tracks. Further, it seems that two
regularly scheduled Turkish Airlines (THY) flights from Chicago and
Toronto to Istanbul were serendipitously at the right time and
place. From their headings as depicted, it seems the
pilots may have gotten a great view
of totality. However, it looks like the angle to the Sun too oblique
for the starboard side passengers to have gotten a view of totality.
-------------------------
Last update: 27 March 2015
RETURN to Glenn
Schneider's Umbraphillia Page